Critical Path Analysis/Examples

From ProofWiki
Jump to navigation Jump to search

Examples of Critical Path Analysis

Aircraft Turnround

Consider the process of turning round an aeroplane after landing.

The following activities need to be addressed:

$\begin{array}{llll} & \textit{Activity} & \textit{Duration (Minutes)} & \textit {Precedents} \\ \hline \text A & \text{Disembark passengers} & 7 & \\ \text B & \text {Unload baggage} & 10 & \\ \text C & \text {Refuel aircraft} & 12 & \text A \\ \text D & \text {Clean cabin} & 15 & \text A \\ \text E & \text {Load catering requirements} & 6 & \text D \\ \text F & \text {Load baggage} & 12 & \text B \\ \text G & \text {Embark passengers} & 14 & \text C, \text E \\ \text H & \text {Final loading check} & 2 & \text F, \text G \\ \end{array}$


The following CPA network diagrams the above task breakdown.

CPA-Network-Example.png

The critical path is the path consisting of edges $\text A, \text D, \text E, \text G, \text H$.