Definition:Critical Path Analysis/Activity

From ProofWiki
Jump to navigation Jump to search

Definition

An activity is a task which needs a certain amount of time to perform.


Start Time

The start time of an activity is the time at which the activity is started.


End Time

The end time of an activity is the time at which the activity is completed.


Duration

The duration of an activity is the length of time it takes to perform the activity.


Precedence

The precedence of an activity is a list of all activities which need to be performed before it.